Sterling Ridge Infrastructure – Civil has been a significant player in the heavy civil construction field for in excess of 30 years. The respective founding corporations boast in excess of eighty years of collective experience in heavy civil construction. Sterling Ridge Infrastructure – Civil has the experience, expertise and extensive resources necessary to manage and execute heavy civil construction projects of any magnitude. Our focus has been the construction of roads, bridges, sewers and watermains. Sterling Ridge Infrastructure – Civil is proud to have been a contributing sub-contractor to many large projects including, the Gordie Howe International Bridge – Canadian Point of Entry Surcharge and Concrete Works, the WDBA Hydro One Transmission relocation, the Herb Grey Parkway and the New Brighton Beach Generating Station in Windsor, Ontario.
Division Services
Heavy Civil
At Sterling-Ridge, we achieve continuous success in the impressive execution of a variety of complex, challenging, and non-conventional heavy civil construction projects. Our services feature collaboration among our group sectors for consistent client convenience and satisfaction.
Expert Solutions for Complex Heavy Civil Projects:
Earthworks
Earth and Rock excavation
Deep Foundations, Pile driving and sheet Piling
Soil stabilization and improvement
Directional Drilling
Demolition
Waste management facilities
Environmental Conservation Infrastructures
Sewers and
Watermains
With dedicated and experienced teams, Sterling-Ridge has installed hundreds of kilometers of linear infrastructure of sewer and watermain systems. Our clients consist of Municipalities, Commercial and Industrial Groups as well as Private Companies and Developers.
Reliable Solutions for Sewer & Watermain Infrastructure:
Water-mains and Sewer construction
Open excavation and trenchless pipe installation
Concrete structures installation
Underground Infrastructure rehabilitation
Municipal and Commercial services
Utility contracting
Road, Culverts and Bridge
Construction
Clients who have complex projects rely on Sterling-Ridge's ability to provide and develop unique solutions. Sterling-Ridge approaches each project with a focus on delivering where others cannot.
Innovative Solutions for Complex Projects:
Cast in Place and Precast concrete structures
Temporary Roads and Bridges
Road construction and rehabilitation
Bridge construction and rehabilitation
Earthworks
R E C E N T P R O J E C T S
EWSWA REGIONAL LANDFILL CELL 5 NORTH CONSTRUCTION
Client Name: Windsor-Essex Solid Waste Authority
Duration: July 2024-July 2025
Project Value: $11.7 Million
-
This project consisted of the excavation and construction of Cell 5 North at the EWSWA Regional Landfill. Work included comprehensive site preparation, earthworks, and the installation of a liner system to ensure environmental protection and containment integrity. The scope involved grading, subgrade preparation, and the placement of engineered protective layers to support the landfill’s long-term operations. Drainage infrastructure and a leachate collection system were also installed to improve environmental safeguards and operational efficiency. This project was completed in alignment with all regulatory requirements and sustainability goals, supporting the safe and responsible management of waste for the region.
WINDSOR’S CITY HALL SQUARE
Client Name: City of Windsor
Duration: July 2024-July 2025
Project Value: $1.6 Million
-
Sterling Ridge Infrastructure Inc. served as the Site Contractor for the redevelopment of Windsor’s City Hall Square. Our work included installing new utilities, stormwater retention, and drainage systems, as well as excavation, backfill, and granular base for the ice rink slab, civic esplanade, and pavilion building. We also completed refrigeration and plumbing line installations for the rink and fountains, roadway re-paving, and site grading.
This project transformed the former City Hall site into a vibrant public space, aligning completion with the City of Windsor’s July 2025 birthday celebration.
LARGE-SCALE WAREHOUSE
Client Name: -
Duration: July 2023-July 2024
Project Value: $13 Million
-
Sterling Ridge Infrastructure Inc. successfully completed the civil construction portion of a large-scale warehouse project in Windsor, Ontario. Groundbreaking began in July 2023, and the building was delivered to the owner on schedule in July 2024.
The project scope included the excavation, cataloguing, removal, and proper disposal of approximately 21,000 m³ of excess soil, the removal, recycling, and disposal of over 1 kilometre of existing storm piping, and the demolition of a decommissioned transformer station. Sterling Ridge supplied and installed approximately 150,000 metric tonnes of granular fill material, over 2.2 kilometres of underground stormwater system, and approximately 1 kilometre of watermain and fire main. The team excavated and backfilled more than 130 pier foundations and 480 metres of footings, prepared the under-slab composition for the 28,000 m² building slab, and graded for roughly 40,000 m² of asphalt parking lot.
SCULLY/ST. MARKS PUMP STATION
Client Name: Town of Tecumseh
Duration: Sept 2023 - Ongoing
Project Value: $19.2 Million
-
The project will be a collaborative effort between Sterling Ridge Infrastructure and Sterling Ridge General Contracting. The primary scope of work is as follows:
Construction of a new stormwater pump station and Outlet
Construction of shoreline protection walls
Reconstruction of Storm and Sanitary Sewer, Watermain, Street Light, and Road along Riverside Drive between Grant Avenue and Arlington Boulevard
Decommissioning of two existing stormwater pump stations
BNA - CONCRETE WORKS
Client Name: Bridge North America
Duration: 2020-2023
Project Value: $32 Million
-
The Concrete Works Project at the Canadian Point of Entry for the Gordie Howe International Bridge includes construction of the footings, piers, walls, slabs, retaining and shear walls for the eleven buildings.
This package includes excavation, backfilling, insulation, waterproofing and dock levelers as well.
ENGINEERING FILL AND SURCHARGE PROJECT
Client Name: Bridge North America
Duration: 2019-2023
Project Value: $34 Million
-
Sterling Ridge Infrastructure Inc. has been awarded the Engineering Fill and Surcharge Package for the Gordie Howe International Bridge from Bridging North America “BNA”. The main scope is to supply and install more than 750,000 metric tonnes of aggregate material and within the site to install and move more than 850,000 metric tonnes of aggregate material.
In addition to the aggregate material, instrumentation devices for monitoring the settlement and ground water pressure have been installed and are part of the scope of work. The main activities are occurring at the Canadian Point of Entry “CPOE” for the Gordie Howe International Bridge in Windsor, Ontario.
In one day, Sterling Ridge Infrastructure Inc. supplied and installed 15,367.40 metric tonnes of aggregate material with more than 70 trailers involved to truck the material from Erie Sand and Gravel in Leamington to the job site at Windsor. Sterling Ridge Infrastructure Inc. also performed 85 compactions tests on the sublots.
The project team has worked more than 12 hours a day, six days a week with full production and efficiency to put us ahead of critical schedule.
LEGACY BEACON
Client Name: Oscar Construction
Duration: May 2023 - May 2024
Project Value: $2.66 Million
-
Excavation and backfill for new legacy beacon building, new storm, sanitary and water service work.
DOMINION BLVD REHABILITATION
Client Name: City of Windsor
Duration: Aug 2023-Dec 2023
Project Value: $5.5 Million
-
Dominion Boulevard from Northwood Street to Ojibway Street. Storm Sewer, Pavement, Watermain and Street Lighting Rehabilitation.
STRONGERTOGETHER
Office Locations
Sterling Ridge Group Inc. 6260 Westar Dr., LaSalle, ON N9J 0B5
DMG Architectural Glass & Metal 2751 Temple Dr., Windsor, ON N8W 5E5
415 Talbot St. West, Leamington ON N8H 4E1
Logistics Inc.
T: 519 - 978 - 3111
E: info@sterlingridgegroup.com
Contact